Skip to content
Discuss sourcing

Small steel plate orders: when to source locally or from Japan

Suppose your workshop needs six steel blanks for a trial. They must arrive at receiving door 2 by 18 June 2027, with mill records you can match to the blanks on receipt.

The local service centre quoted delivery to the workshop, but has yet to confirm the records. The supplier in Japan quoted through dispatch, leaving onward freight and the arrival date open. Send both suppliers the same requirements. Once you know which routes can meet them, compare the prices that are still in play.

Same receiving requirementsLocal routeDelivery quotedMill record unconfirmedJapan routeQuote ends at dispatchOnward freight unquotedBuyer checks both gapsLink record to blanksConfirm arrival at door 2Compare only qualified routes
Same receiving requirements
Local routeDelivery quotedMill record unconfirmed
Japan routeQuote ends at dispatchOnward freight unquoted
Buyer checks both gapsLink record to blanksConfirm arrival at door 2
Compare only qualified routes
Figure 1 — The opening offers have different gaps: match the records to the blanks and confirm the complete route to door 2 by the deadline before comparing prices.

Give both suppliers the same requirements

Ask both suppliers which mill made the steel they are offering. Where your specification limits the approved mills, check the offered source against it. Price material from any other mill as a separate option for approval.

Check both routes What makes an offer usable
Minimum billable order State whether the minimum is pieces, parent plates or weight; show charge and ownership of surplus.
Cutting Name who cuts and whether the quoted quantity is usable blanks; price any buyer-arranged cutting.
Delivery Give an arrival date and itemise the legs not covered up to the same receiving door.
Inspection documents Name the issuer, confirm when the documents will be available, and show how each blank or agreed bundle can be matched to the record by receipt.

JFE Steel’s order guide lists quantity, delivery terms, destination and document arrangements among the items to specify to JFE. SSAB describes cutting among its service-centre offerings. These are reasons to ask each supplier about its actual offer, not evidence of stock, minimum lots or lead times for either route.

SSAB’s Oborniki service centre gives different capabilities for different processes at that site. Ask whether the quoting site will cut the trial lot itself. If it sends the blanks elsewhere for cutting, ask who manages the cutting schedule and who keeps each blank traceable through the handoff.

Decide which route to advance after the replies

Suppose the local centre replies: “We can deliver the blanks, but we can’t provide a mill record that matches them by receipt.” The Japanese supplier adds onward freight and confirms two things: the blanks will arrive at door 2 by the deadline, and the mill records can be matched to them by receipt. The buyer advances only the Japan quote for the trial and checks the material and cut specification before ordering. The local offer is out for this lot regardless of price; it can be revisited for a later lot.

Keep each route in play if it meets the material, cutting, document and arrival requirements, with confirmed stock and an acceptable billing minimum. The same requirements apply if one supplier can meet a condition the other cannot. Do not use a lower price to waive a required document. A missing response calls for a question; a confirmed failure on a mandatory requirement removes the route unless the requirement is formally changed. For a trial followed by repeat orders, ask about replenishment separately: the stock earmarked for the trial tells you nothing about the next lot.

If both routes qualify, compare the total for the same usable quantity at the receiving door, including separately arranged cutting and freight. Keep the charge for unavoidable surplus visible: the price of six needed blanks is not six times a unit price when the supplier bills a full plate.

RFQ text (fictional example)

Please quote six cut blanks to SR-03 Rev A for delivery to our workshop, door 2, by 18 June 2027. Confirm available quantity, the minimum billable quantity and its unit, who keeps any surplus, who cuts and which transport legs are covered. Identify the mill that made the offered steel and the document issuer. Tell us when the records will be available and how we can match them to the blank IDs by receipt. Quote any different material or delivery basis separately. Give replenishment terms separately from the trial.