A new control cabinet: can you quote the power supply before startup is settled?

Suppose a small indexing station has a cabinet layout at revision B and a load list at revision A. The design team has yet to decide whether both actuators must start together. If their startup loads overlap, the current required at the supply’s output may change. Procurement can ask for a quote with a stated startup assumption while the electrical design lead considers what the cabinet must demonstrate.

Ask about the current the actuators draw from the supply output when they start. The input inrush when the supply itself is energized is a separate question. OMRON’s FAQ gives an example where load startup can trigger overload protection even though running current is within capacity.

What a quote that assumes separate starts can tell you

The supplier replies, “This price assumes separate starts. We have not assessed simultaneous startup.” Ask what interval the quote assumes and whether that leaves any overlap in current demand. Use the stated conditions to compare prices. Keep conditions the reply does not cover marked as unassessed.

Request the full model reference and the datasheet and dimensional drawing revisions. PULS’s CP10.241 product page illustrates the kind of documents tied to an exact model number.

From a quote assumption to a production decision RFQ inputsLayout B and load list A Conditional quotePrice assumes separate starts Simultaneousstartup: not assessedProduction order on hold Cabinet prototype reportRecord revised case and tested unit Electrical design owner approvesThen release the production order Start together? Requote
RFQ inputsLayout B and load list A
Conditional quotePrice assumes separate starts
Simultaneousstartup: not assessedProduction order on holdStart together? Requote
Cabinet prototype reportRecord revised case and tested unit
Electrical design owner approvesThen release the production order
From a quote assumption to a production decision Quote against load list A. If simultaneous startup becomes a design requirement, return the revised load list B for a new quote.

Who supplies and keeps each record?

Who What to ask or check What to keep
Procurement Ask for a quote against layout B and load list A Basis for comparing quotes and any unassessed conditions
Supplier State the exact model and assumed interval between starts Quote and revisions of supporting documents
Electrical design lead If simultaneous startup becomes a requirement, agree what to test in the assembled cabinet Prototype results and approval of the model

What to ask in the first RFQ

Cabinet layout B and load list A show the available space, intended mounting orientation, estimated cabinet conditions, and the input and output requirements from the electrical design lead. The controller and sensors are continuous loads. We have yet to decide whether both actuators must start together. Please give the exact model and the datasheet and drawing revisions, the price assuming separate starts, the interval assumed, and whether the quote accounts for overlapping current demand. Identify any unassessed conditions and quote any prototype support separately.

Send load list B if simultaneous startup becomes a requirement

Update the load list to revision B and send the changed requirement back. Ask whether the supplier still proposes the same model and what changes in the quote. The electrical design lead checks what the supplier tested on the unit and agrees on the assembled cabinet’s test cases and pass criteria before the prototype trial. Procurement places the production order after the lead reviews the results and approves the model.