Packaging-machine trial / FAT / SAT brief Revision / date: Buyer / maker / machine configuration: Test purpose and location: Project and test scope Agree: Brief revision; machine configuration; products/formats included; FAT, SAT or a feasibility trial. Record: Test location, configuration and the checks actually completed. Acceptance criterion: [to agree] Actual result: [not yet tested] Owner / disposition / retest: [to agree] Product and samples Agree: Product identity/lot; viscosity and measurement temperature if known; particles; filling temperature; available sample quantity. Record: Actual sample lot and condition; substitutions and their agreed limitations. Acceptance criterion: [to agree] Actual result: [not yet tested] Owner / disposition / retest: [to agree] Film and packet Agree: Film structure/revision/lot; roll specification; packet dimensions; seal layout; number of lanes. Record: Actual film lot, format, tooling and any change from the brief. Acceptance criterion: [to agree] Actual result: [not yet tested] Owner / disposition / retest: [to agree] Fill and measurement Agree: Target quantity/unit; agreed limits; method, sample plan and instrument. Use density if converting mass and volume. Record: Individual readings and sample identities, not only a displayed average. Acceptance criterion: [to agree] Actual result: [not yet tested] Owner / disposition / retest: [to agree] Observation window Agree: Start/end rule; warm-up treatment; duration; stops, restarts and permitted interventions. Record: Elapsed time, stop reasons and intervention log under the agreed counting rule. Acceptance criterion: [to agree] Actual result: [not yet tested] Owner / disposition / retest: [to agree] Output and rejects Agree: Total/accepted/rejected/reworked definitions; counting point; required accepted-pack rate and its time basis. Record: Counts in non-overlapping categories and the actual elapsed-time denominator. Acceptance criterion: [to agree] Actual result: [not yet tested] Owner / disposition / retest: [to agree] Seal and pack checks Agree: Defect definitions; leak/seal checks; method, conditioning and sample positions; separate storage-test scope. Record: Defect location, sample IDs, observations and the results of the specified checks. Acceptance criterion: [to agree] Actual result: [not yet tested] Owner / disposition / retest: [to agree] Changeover and cleaning Agree: Formats/products to change between; start/end state; steps included; authorised operating and cleaning procedures. Record: Time and interventions for the agreed task, with remaining hygiene-validation work identified. Acceptance criterion: [to agree] Actual result: [not yet tested] Owner / disposition / retest: [to agree] Installation conditions Agree: Destination/site; electrical supply, utilities, room conditions and upstream/downstream interfaces to confirm with specialists. Record: Differences from the factory setup; readiness owner and the site checks still required. Acceptance criterion: [to agree] Actual result: [not yet tested] Owner / disposition / retest: [to agree] Evidence and open points Agree: Witnesses; raw records; applicable instrument records; acceptance owner; exceptions; correction and retest/release rule. Record: Result per requirement; unresolved points; owner/date; evidence needed for the next decision. Acceptance criterion: [to agree] Actual result: [not yet tested] Owner / disposition / retest: [to agree] Please identify the conditions you can reproduce, proposed deviations and the evidence you will provide. Please distinguish the trial scope from factory/site acceptance and any separate safety, hygiene or shelf-life work.